Summary
Spring flooding and undersized contractor pumps drove up engineering oversight costs on the Bridge Street bridge replacement. The council released $200,000 from the road reserve fund, and the project is now targeted for December 4 completion.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 14, 2026.
Impact analysis
$200,000 drawn from the roadway capital reserve fund.
Bridge Street residents and school bus routes once the project wraps up.
Future road projects lose $200,000 of reserve capacity.